By Local Democracy Reporter Peter Davison
A controversial waste contract linked to Westbury’s notorious ‘whiff’ could be back on the table after previously being deemed too expensive to escape.
The deal covers the Northacre mechanical biological treatment (MBT) plant, where odour problems have plagued residents for years and prompted intervention by the Environment Agency.
Questions have now been raised over what has changed after councillors were told that exiting the long-term contract with Hills Waste Solutions is “back on the table”.
Waste Transformation Task Group chairman and senior Conservative councillor Dominic Muns revealed the apparent change in direction while reporting to the Environment Select Committee.
He said members had reviewed revised proposals for the contract and sought clarification over what had changed since the options were previously considered.
“Exiting that contract, we were told, was unaffordable, but in terms of the risk matrix it was the lowest risk and the best value long-term,” he said.
“The group was told that actually we may now be looking at exiting that contract, that is back on the table.
“So there were some concerns there as to what’s changed.”
Cllr Muns said the task group wanted the authority to negotiate hard, adding, “Obviously something has changed from last year.
“We want to make sure, if this is an opening offer in terms of that negotiation, we push that as hard as possible.”
The ‘Westbury Whiff’ has become associated with odour problems at Northacre, which treats household waste that has not been separated for recycling.
The Environment Agency has repeatedly investigated complaints and in June linked increased odour to failures involving the plant’s biofilter, which is designed to treat odorous air.
By August, the regulator said it was continuing to detect “unacceptable levels of odour” beyond the plant boundary and ordered Hills to reduce the maximum amount of waste it accepted from 300 tonnes to 215 tonnes a day.
The contract at the centre of the latest discussions is a 25-year landfill-diversion deal with Hills which runs until 2038.
At a Cabinet meeting last December, council leader Cllr Ian Thorn said it would cost £19 million to get out of the contract, describing that as “a price that sadly was far, far too much to pay”.
He subsequently told Full Council that leaving could save money over the longer term but added, “You have to find the £19m first.”
Asked what had changed and whether the £19 million estimate remained accurate, the authority declined to provide details but confirmed negotiations were ongoing.
Cllr Paul Sample, cabinet member for Environment, Climate and Waste, said, “As negotiations are ongoing, we are unable to comment on specific details at this stage.
“We recognise the interest in this facility and will provide further information when there is an update and details can be shared publicly.”
Send us your news!
Help us keep your community connected and informed.
Do you have an interesting story you would like to share? Have you seen something you feel needs more attention? Get in touch with a reporter today!
✉️ Click here to get in touch with a reporterSupport White Horse News
Help us keep your community connected and informed.
Local news is under pressure more than ever. Choose a monthly subscription or a one-off donation to support independent reporting in White Horse News.